Ecolanet Technologies

  • Objective

    The project aimed to construct a 1,830 sq. mtr. Manufacturing Unit for Ecolanet Technologies in Madhyamgram, North 24 Parganas, West Bengal. Designed as per 3D architectural specifications, the facility was developed to support advanced manufacturing processes, ensuring structural integrity and operational efficiency.

  • animation-w4Challenges

    The project posed key challenges, including:

    • Strict completion timelines, requiring seamless coordination across design, procurement, and execution teams within just 3 months.
    • Timely procurement and delivery of materials to maintain uninterrupted construction progress.
    • Deploying the erection contractor on schedule, ensuring smooth execution of all phases.
    • Maintaining high-quality construction standards, adhering to technical specifications and industry norms.

  • Solutions

    Utkarsh India successfully addressed these challenges by:

    • Strategic Project Execution: Followed a structured approach, covering proposal creation, final design submission, fabrication, and erection in an accelerated timeframe.
    • Optimised Logistics & Material Planning: Ensured on-time delivery of raw materials to prevent delays.
    • Precision Manufacturing & Quality Control: Conducted multi-stage inspections, ensuring all components met the highest quality standards.
    • Workforce Allocation & Supervision: Deployed 500 skilled workers with expert technical supervision, ensuring smooth and on-time project execution.

  • animation-w4Conclution

    Utkarsh India successfully delivered a high-quality Pre-Engineered Building (PEB) within the committed 3-month timeline, demonstrating expertise in fast-track industrial infrastructure development. By ensuring timely completion, material precision, and structural excellence, we strengthened our position as a reliable partner in manufacturing infrastructure solutions.