Installation of W Beam Metal Crash Barriers for New Greenfield Highway, Package 4, West Godavari District
-
Objective
To implement a critical safety solution by supplying and installing 60,000 metres of W Beam Metal Crash Barriers along the New Greenfield Highway Package 4, West Godavari District (NH365BG). The key focus was ensuring timely delivery and quality installation within a tight 7-day timeframe, in accordance with all safety standards.
-
Challenges
- Strict Deadline: The project required the delivery and installation of 60,000 metres of W Beam Metal Crash Barriers within just 7 days.
- Logistics and Timely Delivery: Coordinating rapid delivery and installation across the highway project, ensuring the materials were available on time and installations were completed without delay.
- Quality Assurance: Maintaining high-quality standards in manufacturing and installation while meeting the project’s aggressive timeline.
- Documentation and Compliance: Ensuring all materials were accompanied by Material Test Certificates (MTC) and complied with safety and regulatory standards.
-
Solutions
- Timely Delivery and Installation: Effective project management ensured that all 60,000 metres of W Beam SSSB were delivered and installed within the 7-day deadline, with precise scheduling and coordination.
- Quality Assurance: Each batch of barriers underwent rigorous quality control checks, ensuring compliance with both safety standards and technical specifications.
- MTC and Documentation: Provided Material Test Certificates (MTC) with each delivery to guarantee the integrity and specifications of the crash barriers.
- Efficient Logistics and Vehicles: Managed transportation and installation logistics seamlessly, ensuring no delays and that installation teams had the required resources for on-site work.
-
Conclution
The successful delivery and installation of 60,000 metres of W Beam Metal Crash Barriers on the New Greenfield Highway, Package 4, underscored our ability to meet tight deadlines without compromising on quality. Despite the 7-day timeline, the project was completed efficiently, enhancing the safety of the highway in West Godavari District (NH365BG). This achievement highlights our commitment to high standards in safety solutions, on-time delivery, and client satisfaction.