Sterling and Wilson Renewable Energy Limited

  • Objective

    The project aimed to supply and install Tracker Components (Piers for Tracker) at Green Infra Wind Energy Ltd’s site in Jaisalmer, facilitating solar power generation and utilisation, along with EV charging infrastructure. This initiative was crucial in enhancing renewable energy integration in the region.

  • animation-w4Challenges

    The project posed key challenges, including:

    • Strict delivery timelines, requiring the supply and installation of 90 MT of solar tracker components within 45 days.
    • Ensuring technical compliance, particularly with (W 6 X 7) and (W 6 X 12) tracker component specifications.
    • Coordinating logistics and quality control, ensuring timely delivery, adherence to quality standards, and inclusion of Material Test Certificates (MTC) along with the vehicle.

  • Solutions

    Utkarsh India successfully tackled these challenges by:

    • Precision Manufacturing: Fabricated high-quality Piers for Trackers using industry-standard materials, ensuring structural integrity and durability.
    • Streamlined Supply Chain & Logistics: Implemented a structured production and dispatch strategy, ensuring on-time delivery within the 45-day deadline.
    • Rigorous Quality Control: Conducted multiple quality checks, ensuring all components met the highest industry standards before dispatch.
    • Expert Workforce Deployment: Deployed skilled professionals to ensure seamless execution and timely installation.

  • animation-w4Conclution

    Utkarsh India successfully delivered tracker components for Sterling and Wilson Renewable Energy Limited, playing a key role in Jaisalmer’s solar power expansion. This project enhanced renewable energy generation and EV infrastructure, reinforcing our position as a leading provider of high-quality solar structures.